Investment & delivery
From signature to go-live — a programme you can test
Six investor gates. Capital is committed only when geometry, supplier compatibility and commercial rights are proven. Change the start date and working pattern to see the programme respond.

Programme
38 wks
Go-live
25 Apr 27
Peak crew
21
Working pattern
23:00–07:00
Readiness
0%
01 · Programme
Interactive master programme
Mall closed; full access to atrium and façade, no shopper disruption. Typical for live retail. 40 productive h/week.
02 · People
Team mobilisation
Week 19 · 07 Mar 27
21 people
03 · Site
Site layout & installation sequence
Schematic sketch — proposed, not surveyed. Drag the week slider above to see each zone go live.
Engineering
Scaled CAD/IFC model, structural calcs for E01 steel, cable schedules, AV riser diagrams and DMX/IP addressing before any purchase order.
Construction
Hoarded night works: containment, power from approved boards, canopy and façade supports with certified lifting plans.
Fit-out
Cabinet-by-cabinet LED alignment, speaker aiming to the zone map, fixtures patched to universes, rack dressed and labelled.
Commissioning
Witnessed tests, calibration logs, offline fallback and UPS shutdown proven; O&M, spares and passwords handed over.
Safety & quality
Permit-to-work, method statements, daily toolbox talks, ITP hold points signed by a named engineer.
04 · Gates
Six investor gates
GATE 1
Verify site & rights
Scaled architecture; wall / canopy support; AV room; media concession; local rules
✓ No purchase order without verified installation rights, room allocation and commercial inventory rights.
GATE 2
Sell and mock up
Rate-card test; advertiser interest; a full-size display / light sample
✓ Pilot pre-sales and tenant approvals support the target fill; check real ambient visibility and screen glare.
GATE 3
Freeze engineering
Coordinated AV / audio / lighting drawings; loads; SKU schedules; OEM compatibility
✓ Architect, structural, electrical and fire-safety approvals; no outstanding critical interface.
GATE 4
Factory / bench test
Pixel canvas, low-brightness calibration, player / CMS publishing, speaker and lighting patches
✓ Verify full-resolution playback, sensor dimming, restart, offline fallback and log recovery.
GATE 5
Site commission
Audio tuning, photometric checks, final routing, labels, UPS control shutdown
✓ Owner witnesses tests; named engineer signs records; O&M, spares, passwords and training delivered.
GATE 6
Review trading
Monthly gross-to-net cash report and sell-through dashboard
✓ After 90 operational days, compare actual rate / fill / OPEX against the pilot assumptions before expansion.
05 · Readiness
Approval holds tracker
06 · Sources
Source register and credits
Concept & integration design: Engineer Khalil Ajouz | SkyVelor Company. Manufacturer families cited are referenced from published data [M-series references in the master study]; their naming does not imply manufacturer endorsement. Third-party architecture, product marks and tenant imagery retain their respective source attribution. Watermarks identify the proposal origin; they do not constitute a certified digital signature.