Investment & delivery

The investor calculator

A US$100,000 pilot, six screens sold as one network, and a model you can stress-test yourself. Move any driver — every figure below recalculates instantly from the study's formulas.

Capital required

$100,000

Pilot BOQ, incl. contingency

Payback

3.31 yrs

Cumulative cash crosses zero

Five-year IRR

15.8%

Zero terminal value — conservative

NPV @ 12%

$9,791

Clears the hurdle rate

01 · Calculator

Set your own assumptions

Start from a study scenario

Revenue drivers

Costs & terms

Capital recovery curve

5-yr cash $153,019 · multiple 1.53×

BREAK-EVENY0-100kY1-71kY2-40kY3-8kY418kY553k

Year-one gross to net [C]

Advertising
$53,040
Activation
$10,000
Mall share
−$9,456
Commission
−$6,304
Operating
−$18,000
Cash generated
$29,280

Year-one cash

$29,280

5-yr profit after capital

$53,019

5-yr ROI

53%

02 · Risk

Sensitivity map — payback by rate and fill

FILL ↓ · RATE →$600$700$850$1,000$1,150$1,300
40%
50%
60%
70%
80%
90%

Green ≤ 4 years · gold 4–5 years · red = not recovered in five years. Uses your current cost settings. Click a cell to load it.

03 · Detail

Five-year cash flow

YearGrossMall shareCommissionOPEXReplacementNet cashCumulative
Y1$63,040−$9,456−$6,304−$18,000—$29,280−$70,720
Y2$65,562−$9,834−$6,556−$18,540—$30,631−$40,089
Y3$68,184−$10,228−$6,818−$19,096—$32,042−$8,047
Y4$70,911−$10,637−$7,091−$19,669−$7,500$26,014$17,968
Y5$73,748−$11,062−$7,375−$20,259—$35,052$53,019

+4% revenue / +3% OPEX per year · $7,500 Y4 replacement · no resale or terminal value credited.

04 · Why it holds

What protects the investor

Conservative by design

Zero terminal value, no contingency recovery, Y4 replacement already deducted.

Mall aligned

The mall earns a revenue share — it is motivated to sell and protect the network.

Scalable

The pilot proves rates and fill before the whole-mall scope is committed.

05 · Capital

US$100,000 pilot BOQ

IDDescriptionQtyUnit allowanceTotal
P01Indoor COB hero LED, 3.00 x 1.6875 m1$22,500$22,500
P0255-inch LCD displays + five fitted enclosures / mounts5$3,200$16,000
P034K LED sending / processing package1$4,500$4,500
P04Certified local media players6$450$2,700
P0512-speaker / four-zone audio package1$7,500$7,500
P06Selected architectural-lighting pilot1$8,500$8,500
P07Decorative seating / feature-light pilot1$2,500$2,500
P08Network, managed access, rack and control UPS1$5,500$5,500
P09Pilot installation, power and containment1$6,500$6,500
P10Design, CMS setup, launch content and training1$5,500$5,500
P11Logistics, commissioning spares and contingency1$18,300$18,300
Pilot total$100,000 [C]

Planning allowances, not manufacturer quotes. R01 suspended ring is optional and excluded from both budgets.

06 · Expansion

Whole-mall reference scope

ItemQty / basisUnit allowanceExtended
Outdoor LED panels59$3,000$177,000
Indoor LED panels7.4925$4,500$33,716
Eight indoor LCD poster assemblies8$2,400$19,200
Four touch-directory assemblies4$4,500$18,000
LED processors, OEM fibre interfaces and local backups1$40,000$40,000
22 media players22$450$9,900
Audio speakers, amplification and DSP1$44,200$44,200
Architectural lighting and local power/data controls1$106,000$106,000
Decorative lighting1$20,000$20,000
MDF / IDF network, racks, UPS and monitoring1$35,000$35,000
Structural allowances, mounting, electrical and installation1$90,000$90,000
Design, content setup, tuning and training1$35,000$35,000
Allowance$628,016.25
Contingency$94,202.44
Master total$722,218.69 [C]

Listed lines sum to $628,016; the recorded allowance reflects unrounded quantities. No return is modelled on the master scope.